It’s been another month of progress on Highway 114 road construction. Crews continue with utility replacements in the city of Lowry. As they get closer to the Highway 55 intersection with storm sewer and water main replacements, motorists can expect to encounter lane closures and flaggers on Highway 55 while crews work near that intersection. 

Concrete crews will be on-site in Lowry this week to begin forming up curb and gutter, and will start pouring mid-week in town.

South of Lowry, crews will be completing the remaining centerline culvert replacements between Lowry and 150th Street. A reminder that each culvert takes 1-3 days and the road will be impassable to all traffic at the culvert sites. 

And starting today, Monday, Sept. 9, crews will begin milling and paving, with the operations starting near County Road 24, working south toward Starbuck. 

Residents should travel with extreme caution in this area, and if you don’t have a destination on Highway 114, please stick to the detour route.